Operational since autumn 2025, the system provides high-availability flexibility services, supports renewable curtailment reduction, and delivers fast-acting stability to the Belgian electricity network. With enough capacity to deliver 75MW continuously for four hours, Harmignies BESS plays a major role in supporting the region’s long-term grid resilience.
The project also sits close to the 50MW/200MWh Wallonia BESS site, where we have previously supplied fourteen Wilson MV Transformers and a Wilson Power Transformer, marking Harmignies as the latest milestone in our ongoing contribution to Belgium’s energy storage landscape.
The project, located in an area that was previously a cement factory, consists of eighty two Tesla Megapacks 2XL connected to the grid through twenty two 4.4MVA Wilson T2 Ecotrans® Large Distribution Transformers.